Project Schedule

 
Item
Date
Phase A - Major Drainageway Planning -
Development of Alternate Plans
Baseline Hydrology Report (Final)
5/21/2007
Draft Phase A Report
9/11/2007
Final Phase A Report
2/8/2008
Select Best Alternate Plan
4/1/08
Final Phase B Report    
Summer 2008
Final FHAD Report        
3/21/08
   
Phase B - Major Drainageway Planning -
Conceptual Preliminary Design
Select Best Alternate Plan
9/3/2007
Draft Phase B Report
11/9/2007
Final Phase B Report
12/9/2007
Flood Hazard Area Delineation
Draft FHAD Report
5/7/2007
Submit Final FHAD Report
7/1/2007